More frequently home
owners are installing hardwood in the great room and office
areas. Texture and color are easily achieved through the use of
area rugs, bright paints and fabrics. In addition, hardwood is
extended through the master suite and children’s bedrooms,
especially if any member of the family experiences breathing
problems or allergies.
We normally install
hardwood right after the drywall is sprayed. It is critical that
all hardwood acclimate to the current temperature & moisture
level of the home, so it
will be necessary to have a controlled
environment at this time. We will need to
deliver your hardwood
2-14 days prior to installation, depending on the season &
width. The hardwood must be placed inside the home, not in the
garage or basement.
The wood is then
installed and the remaining
construction of the home is finished
on top of the kiln dried flooring. The sanding and finishing of
the floor will happen very close to your scheduled move in date.
Depending on the finish option you choose, we will need two days
to complete the finishing process. We use dustless sanding which
minimizes any final clean-up. |